Data center construction is constrained by time, not just permits
Steve Tusa compares the data center pipeline with the tiny amount of Texas capacity already energized and says projects take years to build.
The episode’s best minutes
Full analysis- 3:59Liquid cooling has become essential for dense AI data center racks7 min
- 22:36Data center construction is constrained by time, not just permits8 min
- 19:15AI demand is driving semiconductor reshoring more than incentives3 min
- One more moment in the full episode
“As of the middle of this year, five was lit up. Five out of the 375.”
Takeaways
- The U.S. data center pipeline is far larger than the existing installed base.
- Texas had only about 5 gigawatts lit out of a 375-gigawatt queue.
- A gigawatt-scale project can take around three years to energize.
About this segment
Steve Tusa compares the data center pipeline with the tiny amount of Texas capacity already energized and says projects take years to build. He sees demand and returns as the bigger debate than an immediate political stop to construction.
Steve Tusa is an industrials analyst at Wells Fargo.

Steve Eisman, Host
From “The Industrials Riding the AI Data Center Boom with Steve Tusa | The Real Eisman Playbook Ep 85”, Nov 23, 2026. Watch the full episode
Answers “Is there enough power for AI?” See all 61 answers
Thanks. We'll look at and fix what's off.
Transcript
Transcribed by machine (Whisper) from the episode’s audio, so a word may be off here and there.
- 22:39
I get, as I'm reading everything, there are people out there who are saying there are massive delays in the building of data centers. The politicians are pushing back. But it's very hard to get real hard data as to what's going on. From the people that you speak to, what are you hearing? Sure. First of all, keep in mind that the pipeline now of those who want to build and those who have either procured land, filed permits, is like 450 gigawatts.
- 23:13
Let's define things. What's a gigawatt? A gigawatt is 1,000 megawatts. Okay. And when this industry started, when we started this whole gambit, the entire industry... The entire data center industry in the U.S. was taking up 20 gigawatts. 20 gigawatts. Which was 1% of the power usage of our entire country. Okay, so... 20 gigawatts. So, prior to AI, maybe... Installed base. Installed base. So, if we were going back to like 2020 or something like that...
- 23:47
Yeah, 23 or something. Yeah, 22, 23. The entire data center was using 20 gigawatts of power. That's about 1% of the... And that's 1% to 2% of the entire U.S. Of the entire United States. Of the energy. Now, where are we? Go ahead. Finish what you said before. Say it again. And we were building. So, that's installed base. So, let's just ... Sometimes people look at installed base growth. It's like, I don't think that really matters for my companies.
- 24:11
What matters is how much you're building. Right. That was built over 20 years. The 20s. Yeah. So, they were building ... One a year. They were building like one to two a year. Right. Okay. We are now talking about a pipeline that's 450 ... Gigawatts. Gigawatts. Right. So, it is 20 times. 20 times. what existed in 2023. It's massive. So the point is, you don't just show up and throw 100 gigawatts up in a year or two or even three.
- 24:40
Right. It takes time. Under the best of circumstances. Yes, absolutely. So it's kind of a strange thing because on the one hand, the bear case is there's a bubble and it's going to implode. Right. But on the other hand, the bear case is we can't build this stuff fast enough because we have delays. Well, in law school, we called that arguing in the old term. my dad's a lawyer so i don't know i went to law school that was one of the first things i learned you say they they would tell you argue it's it's nothing there's not ethics here you're just making an argument you can argue in the alternative so so that's what this is arguing in the alternative sometimes i see when i see arguing in the alternative is basically like i i like to understand what and as my dad's a lawyer i kind of i i like debates and i i like going back and
- 25:27
forth and having a thesis and trying to figure out if I'm right or wrong. And those two things can't be true. Oh, no question. At the same time. So, there's something- Either there's a bubble, there isn't a bubble, or there's real demand, but this stuff is so complicated to build and so difficult and the permitting that you're not going to be able to meet the demand. I have one person- And that's the other argument.
- 25:55
Let me bring this all together in one place, Texas, where everybody talks about the politics and how Texas might do a moratorium, or they're looking at extra analysis of permits. Yes. Right? So, Texas has its own queue of about 370 gigawatts. Out of the 440s? So, my 440 is a little different. Oh, okay. My 440 is web scrape, permits, land buys. So I'm kind of like just looking for all news flow, and I'm doing my own math and adding that up.
- 26:31
They're 375. That's your database. That's my database. Okay. The 375 is Texas official utility ERCOT documents. Okay. So that is what they're seeing come through their pipeline. So in other words, they get the permits. Yes. They added it all up, and it's 375. But what I'll tell you is this. As of the middle of this year, five was lit up. Five out of the 375. Five. Yes. And another- I just want to say one thing.
- 27:01
Learned in grammar school, five is a lot less than 375. Don't ask me to do percentages. Just got to point that out. Don't ask me to do a percentage on that. I'm not good with math on the fly. And then there's three gigawatts that is approved to be energized. So let's just pretend it's eight to 10. Let's call it 10. Let's just call it 10. Let's be generous and call it 10. Okay. So, this all comes together and you say, okay, if you're sitting there and you have 300...
- 27:30
75 gigawatts staring you in the face, and you only have 10 that you're comfortable with. As somebody who's trying to manage this queue and maybe stay elected, don't you think you have incentive to go out and say, guys, we need to tap the brakes on these permits? And I could literally come in there and say 200 gigawatts are not happening, and you still have a move from 10 to 200. I'm just saying these numbers are so large.
- 28:00
And they can't happen in the near term anyway. Right. So now let's backtrack for a second. So you've got 10 basically existing, more or less. That are now lit up. They're lit up or they're about to plug it in. One more thing for that. Yeah. Stargate, the one everybody talks about in Abilene. So what's Stargate? So Stargate is this Crusoe project, Horweave and Oracle are involved here. Oh, okay, okay, okay.
- 28:23
So this thing, we got an update on that. They broke ground in June of 24, and that's an 800 to a gigawatt of IT coming on. They're only 75% done. In terms of construction? Yes, lit up, fully energized. This stuff just takes a long time. Takes three years. Gigawatt takes three years. Okay. Let me backtrack for a second. Let's take the 375. Let's say to meet what apparently is the AI compute demand, let's imagine the 375 would have to be built over a certain period of time, it just sounds like what you're saying is going to take longer than what people think it's going to take.
- 29:03
Yes. So, that's key on the supply side. And I think this is about supply and demand. Right. That's key on the supply side. I do not think that anybody right now is saying that there is too much supply and there's a supply overhang. I think the market is worried that at some point down the road, that the demand is not going to be there, because you and I will kind of get sick of AI and say, this just isn't doing it for me, so then maybe my boss comes to me and says, you've got to stop using as much as you're using it, it's costing too much.
- 29:37
So, I think it's a little more of a demand debate and the returns, ultimately, as it comes on it. But it is not. The supply side is... And in Texas, I do not believe that they are acting to the point where there are projects that are in flight that are now... like, okay, shovels down, guys, we've got to evaluate. I think there's plenty of room for it to grow. And I'm just trying to give you an idea of the supply side and the politics of it.
- 30:10
I'm not arguing about there isn't room to grow. My argument is just that it just takes a long time. Yes, but I'm saying right now, the big debate is the politics side. And in Texas, which is where this all comes together, I don't think there is a political influence there that we have to really worry about, at least in the near term. I don't know if things change, but right now, steady state, there's a lot going on.
- 30:33
And just keep in mind, permitting is local. Of course. So, it really depends on, if you're a county over here and I'm a county over here, we could have different views. Right. But that is where the rubber hits the road. So, just keep that in mind.