Texas data centers may have to bring their own power
Ed Hirs argues that ERCOT rewards scarcity rather than reliability, while new data-center demand strains the grid.
The episode’s best minutes
Full analysis- 22:19The Nvidia allegations go beyond an executive's personal conductPro pick 6 min
- 15:02Texas data centers may have to bring their own powerPro pick 4 min
- 7:29AI borrowing is changing the credit marketPro pick 5 min
- 2 more moments in the full episode
“So on ERCOT now, it's almost 40 gigawatts of solar farms, almost 40 gigawatts of wind farms, and 21 gigawatts of short-term battery storage.”
Takeaways Pro pick
- ERCOT's market design can send prices soaring when electricity is scarce.
- New gas turbines face a three- to five-year wait.
- Texas has nearly 40 GW each of solar and wind, plus 21 GW of batteries.
One of Pro's picks, open to you here. Try Pro free for 7 days
One of Pro's picks. The rest of the summary and the 3 takeaways are in Real Alpha Pro; the video, the quote and the transcript stay free.
Read it with Pro, 7 days freeAbout this segment
Ed Hirs argues that ERCOT rewards scarcity rather than reliability, while new data-center demand strains the grid. He explains why new gas plants are slow to arrive and points to Texas's growing solar, wind and battery capacity.
Energy Fellow, University of Houston
- PS
Paul Sweeney, Host
- SF
Scarlet Fu, Host
From “AI Stocks Rebound as Fed Hike Bets Return | Bloomberg Surveillance”, Nov 11, 2026. Watch the full episode
Answers “Is there enough power for AI?” See all 61 answers
Thanks. We'll look at and fix what's off.
Transcript
From the transcript Bloomberg Surveillance publishes with the episode.
- 15:05
So, Ed, one of the big issues here for just the global markets is AI and the energy needed to support AI in these data centers here worldwide. What's your view of the electricity market and the grid here in the U.S.? I know Texas has its own grid. I mean, you guys stand, you're independent there, but how do you think about that?
- 15:27
Well, since 1938, Texas has had its own grid for the most part. It covers about 85% of Texans. And in essence, we have two operating models. One is ERCOT, the Electric Reliability Council of Texas. And it operates with an old-style Soviet Union linear programming model that minimizes the price or the cost, if you will, minute by minute. It really doesn't look ahead. We separated the generators from the consumers and did this 20-odd years ago. The governor was a C-minus econ student at Yale at the time. And it's a market that rewards scarcity, not reliability. And so as the market gets really tight, the price goes way up. There's a huge, I mean, tens of billions of dollars have been funneled over to bonuses and stock buybacks versus building new power plants.
- 16:24
So ERCOT has to rebuild. It has to build a new market following the horrible freeze in 21, the grid failure that killed 246 cost of state, up to $ 200 billion in damages. Governor Abbott appointed an independent guy to run the Public Utility Commission. He said this market needs to be scrapped, but nobody liked his proposal. So they're still in the legislature wrestling with this. And now we face the new demand from data centers. The ones that are already in Texas have driven up the wholesale price of electricity for everyone. Governor Abbott did a full 180 in the face of bad polling numbers. And decided to put a moratorium on the addition of new data centers.
- 17:11
You know, I think what's going to happen in ERCOT and PJM, MISO, SVP, other grids, the data centers are going to have to bring their own power plants. And again, as we look at Texas, we've got ERCOT. And then we have these little pockets that don't work in the ERCOT market or not part of it. Intergy, which is on East Texas side. El Paso Electric, the municipals, Austin and the city of San Antonio, those residents pay more than 20% less than the rest of us in ERCOT.
- 17:42
So how come they get a better deal than those of us in the so-called deregulated markets?
- 17:48
Yeah, so these are all questions and concerns that led to the change in power in Texas overall. It all added up.
- 17:57
That women's health, you know, the maternal death rates in Texas are worse than nations in Africa.
- 18:06
So my question here then, as you mentioned, the data centers will need their own power plants. How likely is that? I mean, how.
- 18:15
Do we see that happening in the next year, in the next two years? It's going to be very difficult if they're using gas-fired power plants because there's now a three- to five-year lag time in lining up the new turbines. What some entrepreneurs are doing is they're stripping engines from the old jet aircraft out in the boneyard in Arizona and reconfiguring those. Solar is expanding dramatically and rapidly, and batteries are fabulously.
- 18:44
So on ERCOT now, it's almost 40 gigawatts of solar farms, almost 40 gigawatts of wind farms, and 21 gigawatts of short-term battery storage. That's what's driving the growth in the Texas electricity market. Talk to us about refineries.