Kirian Mischke-Reeds says data-center financing depends on refinancing construction debt and sustained AI demand, with rising risks likely to drive consolidation.
SOSwitched On · Tom Rowlands-Rees
- Kirian Mischke-Reeds is an analyst on BNEF's Finance and Investment team.
The best minutes
- 10:16Guarantees and short-term debt create refinancing risk7 min
- 20:32NVIDIA supports an AI ecosystem beyond its biggest customersPro pick 3 min
- 30:36AI returns and project execution will test the data center boom4 min
Also worth watching
- 4:46Hyperscalers are turning to debt as data center spending grows2 min
- 7:22Project finance ties construction debt to a specific facility3 min
- 26:20Private credit fills gaps in data center financing3 min
Skip the opening setup and financing totals, the refinancing follow-up and share-price discussion, and the closing recap and legal disclaimer.
Full analysis · 6 min read
Real Alpha · Nov 24
Kirian Mischke-Reeds says about $1.8 trillion was raised
- Major developers raised about $1.8 trillion in external financing between 2020 and the first half of the year.
- The total covers financing by about 125 developers, not construction spending or necessarily project-specific financing.
- Debt coming due from 2029 to 2030 tests whether projects can refinance affordably.
Free with an account
Read the rest of the analysis
6 sections, the 3 other voices it tests Mischke-Reeds against, and what it means for you. Every episode we cut gets one.
Check your inbox
We sent a link to your address. Click it to finish signing up. Not there in a minute? Look in spam.
or
Signed up before? The same buttons sign you in. The episode, its moments and the transcript stay free.
External financing does not measure construction spending
BNEF's headline is about $1.8 trillion raised by the largest data-center developers. Mischke-Reeds said the financing covered the period from 2020 through the first half of the year, across about 125 developers.
That is not a tally of construction bills. He said the financing was raised by data-center developers, but was not necessarily data-center-specific financing.
The distinction reaches beyond whether a dollar can be assigned to a named facility. The total does not establish that every dollar funded data-center infrastructure.
The host checked whether the $1.8 trillion meant spending. Mischke-Reeds answered that much more had been spent, without giving another total.
That answer reinforces the caveat rather than filling it in. The figure tracks external capital raised, not spending or completed capacity.
He called the sample representative, but said it did not cover everybody. So the number measures fundraising across major developers, not assets delivered.
Our read
The figure marks fundraising scale, not installed infrastructure. Treat it as a capital-market signal, not a project-spending ledger.
Hyperscalers are borrowing beyond free cash flow
The funding shift is striking because hyperscalers once relied on their own cash generation. Mischke-Reeds said they generated tens of billions of dollars in free cash flow each annually.
He said they had put basically all of that free cash flow and more into the data-center buildout. Meta, Amazon and Google had become free-cash-flow negative, he said.
That means those companies were spending more than they generated. Bond issuance followed, mostly from 2024, and accelerated quickly.
This is evidence of investment outrunning current cash generation, not proof that their operating businesses stopped being profitable. Mischke-Reeds described the hyperscalers as exceptionally profitable businesses.
For finance teams, the distinction matters. A profitable company can still borrow when a buildout grows faster than its internally generated cash.
On Bloomberg Surveillance in November 2026, Financial Times editor Robin Wigglesworth described AI as shifting toward debt finance. He also warned that the hot private-credit market contained bad deals.
Our read
The episode shows a financing mix changing under heavy capital demands. Borrowing alone establishes neither distress nor attractive project returns.
Construction debt creates a concentrated refinancing test
Project finance links a loan to a specific project and often to a contracted customer. Mischke-Reeds said an offtake commitment can give a bank a clear repayment source.
That structure can ring-fence project liabilities, but it does not remove execution risk. He pointed to permits, power connections and equipment delays during construction.
A colocation shell can have a contracted customer before chips are installed. Its facility revenue is distinct from a neocloud's later sales of computing capacity.
A delay can still matter if it pushes completion, contracted revenue or lender confidence past a loan maturity. The refinancing risk is conditional, not an inevitable gap before workloads begin.
Mischke-Reeds said construction loans may run for five or six years. He identified a concentrated wave of debt coming due between 2029 and 2030.
For neoclouds, he described the amount coming due as rising from almost nothing to about a 19-fold increase year over year. He did not give the exact amount.
He gave a conditional cost example. Refinancing may become more expensive if borrowing rates are two or three percentage points higher because Treasury rates have risen.
“that's one of the risks that we pointed out is just how much debt is actually coming due in a short window”
Our read
The risk is that timely completion, demand and lender appetite may not support affordable refinancing when debt matures. Maturity arrives whether or not a project is ready.
NVIDIA's support takes distinct financing forms
Mischke-Reeds said NVIDIA had disclosed about $109 billion in credit-back guarantees. Most, he said, was a residual-value guarantee for Ohio's Ports Technology Campus, with OpenAI as tenant.
He described the campus as ten gigawatts nominal and, he thought, eight gigawatts of IT capacity. The guarantee helped make the tenancy acceptable to the power provider and developer.
Separately, NVIDIA disclosed $36 billion in compute commitments to neocloud customers. Those are commitments, not evidence that $36 billion of compute purchases has already happened.
The guest said these commitments can provide a revenue floor. He also said customers can take a better deal, while NVIDIA may share in the upside.
These instruments do different jobs. Guarantees can support creditworthiness, while compute commitments can support expected revenue.
NVIDIA sells chips and supports neocloud capacity beyond its biggest customers. The arrangement ties a chip supplier to the ecosystem its products help enable.
Bob Michele, speaking on Bloomberg Surveillance in November 2026, said compute-leasing borrowers often lack cash flow. His account helps explain why stronger counterparties can matter to lenders.
Our read
Guarantees support borrowers' credit, while compute commitments can support potential revenue. Both connect financing to companies with an interest in expanding AI capacity.
Private capital fills gaps but mixes funding types
Mischke-Reeds emphasized private financing for colocation providers and especially neoclouds. It can help when investment-grade support or conventional bank financing is unavailable.
For most neoclouds in BNEF's sample, private sources supplied almost all financing. That category included venture or private-equity investment as well as private credit.
He said CoreWeave and, he believed, Hut 8 were exceptions. He thought each had less than 50 percent of its financing from private sources.
Those sources are not interchangeable. Equity does not create the same scheduled repayment obligation as credit, so a blended financing share can obscure debt exposure.
Private lenders can provide a marginal dollar and more flexible structures. But opacity makes it harder to compare borrowers and assess what sits behind reported financing totals.
For example, Meta's Louisiana joint venture used a special-purpose vehicle. Blue Owl supplied 80 percent of the money, and that vehicle raised debt.
Mischke-Reeds said the debt sat outside Meta's balance sheet. He also described Meta as guaranteeing the data-center development, a separate legal entity.
That project guarantee does not establish that Meta guaranteed all of the vehicle's debt. Still, an off-balance-sheet structure does not mean the sponsor has no connection to project risk.
Our read
Private capital expands funding options, but reported shares can mix equity and debt. A special-purpose vehicle changes where debt sits, not necessarily every sponsor obligation.
Mischke-Reeds expects consolidation as returns are tested
Mischke-Reeds expects some consolidation and said some firms may go out of business. His forecast rests partly on the uncertain near-term economic return from AI.
He called the next 12 months a major test of whether AI generates enough short-term value. That return flows through the chain, from AI labs to cloud providers and colocation firms.
Power access, construction execution and local opposition add pressure. A delayed project can face both uncertain revenue and a loan maturity approaching.
Mischke-Reeds said markets were repricing risk. He thinks completed projects will command a premium, given near-term demand for computing capacity.
By contrast, he said the market was starting to worry about delayed projects. The completed-project premium is his expectation, not a settled market result.
CoreWeave's credit-default-swap prices had come down somewhat from a few weeks earlier. At that earlier point, they implied a 50 to 60 percent default probability over five years.
Mischke-Reeds stressed that this was a market-implied signal, not a forecast. He also said CoreWeave bonds were trading near distressed levels.
Gil Luria, on The Real Eisman Playbook in November 2026, said CoreWeave's low returns could not cover rising borrowing costs. He contrasted it with Nebius's lighter debt and profitability focus.
Our read
The guest describes a market sorting projects by completion, demand and credit support. Broad AI demand does not ensure every borrower can refinance on viable terms.
What it means for you
- Map debt maturities. Build a project-level schedule through 2030, separating construction loans from expected refinancing. The episode identifies a concentrated maturity window from 2029 to 2030.
- Separate support types. Track guarantees, compute commitments, equity and tenant contracts separately. NVIDIA's disclosed figures show why combining them can hide different exposures.
- Stress delayed builds. Model construction delays alongside higher borrowing rates. Check whether contracted revenue and lender appetite still support refinancing when debt matures.
- Test demand quality. Compare signed offtake commitments with project readiness and customer credit. A tenant, guarantor and completed facility perform different roles.
What to watch
- Debt maturities and refinancing costs from 2029 to 2030.
- Whether financing terms diverge between completed projects and delayed builds.
- Whether AI returns, construction execution and local acceptance support debt already raised.
Send this to your CFO, infrastructure lead and board finance committee.
Watch the minute where Mischke-Reeds gives the financing total.
Written by Real Alpha from the episode's transcript and the other moments it links, then checked against the transcript. Quotes are the speaker's exact words.
Minute by minute
A Pro write-up, open to you here. Try Pro free for 7 days
A Pro write-up. The minute by minute is in Real Alpha Pro; the episode, its moments and the transcript stay free.
Read it with Pro, 7 days free- 2:23Financing reached $1.8 trillion
Mischke-Reeds says BNEF tracked about $1.8 trillion in external financing raised by 125 of the largest developers from 2020 through the first half of the year. He distinguishes money raised from capital expenditure: financing can precede spending and is not all tied to individual data-center projects.
- 4:46Developer types shape funding needs
Mischke-Reeds groups developers into hyperscalers, co-location providers, neoclouds and other cloud companies, each with different financing needs. He says Meta, Amazon and Google have turned to bond markets since about 2024 as their data-center spending has outpaced the free cash flow they generate.
- 7:27Project finance ring-fences risk
A data center needs land and power, then a powered shell and chips, with financing attached to each stage. Mischke-Reeds describes project finance as lending against a project and its contracted customer, with liability ring-fenced to that project.
- 10:12Guarantees support smaller developers
Mischke-Reeds says investment-grade companies have increasingly supported unrated or lower-rated developers. He cites about $109 billion in credit guarantees disclosed by NVIDIA and a Meta guarantee for its own project, which he says gave Meta more operational flexibility.
- 13:32Guarantees anchor uncertain tenants
Mischke-Reeds says most of NVIDIA's disclosed $109 billion in guarantees is a residual-value guarantee for the Ports Technology Campus in Ohio. The project has 10 gigawatts of nominal capacity and 8 gigawatts of IT capacity; he says the guarantee helped secure OpenAI as its tenant despite uncertainty about the company's finances.
- 15:28Construction debt comes due soon
Mischke-Reeds says co-location providers have raised more debt than hyperscalers, much of it short-term construction finance. He flags a concentration of maturities in 2029 and 2030 and says neocloud debt due rises sharply from near zero.
- 17:41Refinancing depends on execution
Refinancing after construction can bring cheaper capital, Mischke-Reeds says, but it depends on continued interest in AI and strong project fundamentals. Higher Treasury rates can also raise refinancing costs, while delays or budget overruns can undermine a project's value.
- 20:32NVIDIA backs a broader ecosystem
Mischke-Reeds says NVIDIA disclosed $36 billion in commitments to buy computing capacity from its neocloud customers, creating a revenue floor for them. He says NVIDIA has also taken equity stakes in neoclouds, in part to support a wider AI-computing ecosystem beyond the hyperscalers.
- 24:43Private markets fill the financing gap
Mischke-Reeds says neoclouds and hyperscalers compete for AI lab and cloud customers, while co-location providers need investment-grade tenants or guarantors to secure financing. Private capital is opaque but central: for most neoclouds in BNEF's sample it supplied close to 100% of financing, versus less than 50% for CoreWeave and Hut 8.
- 27:50Special-purpose vehicles hold project debt
Mischke-Reeds says special-purpose vehicles are a common way to hold a project's assets and contracts, and can also support asset-backed securities. He describes Meta's Louisiana project as a joint venture vehicle in which Blue Owl put in 80% of the money; the vehicle raised debt outside Meta's balance sheet.
- 29:19AI financing may consolidate
Mischke-Reeds expects some consolidation and says the next 12 months will test whether AI generates enough near-term returns. He says markets may reward completed, stable projects while growing wary of delayed ones. A few weeks earlier, CoreWeave credit-default-swap prices implied a 50% to 60% default probability over five years, which he stresses was not a forecast; he also says hyperscaler bond spreads widened and Oracle's 20-year bond spread doubled since February.
Published Nov 24, 2026.
Transcript · 33 min read
Switched On, hosted by Tom Rowlands-Rees, with Kirian Mischke-Reeds.
From the transcript Switched On publishes with the episode.
This is Tom Rowlands-Reese, and you're listening to Switched On, the podcast brought to you by BloombergNEF. The global data center build-out is producing some staggering numbers. BloombergNEF estimates that the largest developers have raised around $ 1. 8 trillion in external financing since 2020, with even some of the world's most profitable technology companies increasingly turning to capital markets to fund their expansion. But raising that much money also creates risk. Much of the debt financing construction is relatively short-term and will eventually need to be refinanced, while increasingly complex guarantees are helping smaller developers continue raising capital. Financial markets are already beginning to price in greater risk, raising questions about which developers and financing models can withstand the next phase of the build-out. So, how is the AI infrastructure boom being financed and how sustainable is it? On today's show, I'm joined by Kirian Mischke-Reeds, an analyst from BNEF's finance and investment team, and together we discuss findings from his recent note, Financing Compute, the 1.8 trillion bet on data centers. BNEF clients can find this report and other finance and investment material by heading to BNEF Go
on the Bloomberg Terminal or BNEF.com. If you'd like to learn more about how BNEF approaches strategy research on the energy transition, including developments in commodity markets, trends across different sectors, and the cross-cutting technology shaping the future, you can find more information on BNEF.com. And if you'd like to speak with a member of our team about becoming a client, email us at sales.BNEF at bloomberg.net. But for now, let's unpack the extraordinary sums of money financing the global data center boom. Kirian, welcome to the podcast. Thank you. Now, I have some notes that Cam, our producer, prepared for us, and there are some numbers on these notes.
Big numbers. They are staggeringly big numbers. I think that's the starting point for this podcast. It's like, imagine the biggest number you can think of and then multiply it by several billion, and you might be approaching some of the numbers involved here. I joke, but the size of these numbers... kind of is a feature of this story. So what are these big numbers we're talking about? It's the amount of capital that has been raised to support the global build out of data centers. So hit us with a few numbers just to scare everyone. So everyone freaks out and then maybe we can like, once people's minds are unblown, we can kind of start figuring out how to make sense of these numbers.
Read the whole transcript
I like that approach. Hit him on the head with a number and then walk back from there. So yeah, as you mentioned, very big number. Our research has shown that the largest data center developers have raised about $ 1. 8 trillion, that's trillion with a T, just between 2020 and the first half of this year. That's obviously a huge number. Yeah, that's a huge number. And I think... Important to focus here, like this is just financing, right? This is external financing. A lot of the times when we talk about data centers, we're talking about CapEx or capital expenditures, right? And so that's one side of the equation. That's how much money you're actually spending on data center infrastructure, artificial intelligence infrastructure. The financing is kind of the other side. It's like, where are you getting the money? And so we think this is a huge number. It doesn't cover everybody, but it's about the 125 largest data center developers globally.
So just to clarify what we mean, particularly for people who are sort of less familiar with concepts of project finance, we're not saying that 1.8 trillion has been spent. It's 1.8 trillion has been kind of. Much more has been spent. Much more. Got it. So what's the difference between what's been spent and this 1.8 trillion we're talking about?
So there's actually a really important disclaimer here. And that is that that number talks about financing that has been raised by data center developers, and not necessarily data center specific finance. And the distinction there is important. It's hard to earmark everything, every dollar to a specific data center project. And so we looked at the largest developers, and that includes the hyperscalers are well known, you know, Meta, Amazon, Microsoft, Google, but also includes some of the smaller players that are actively building their business. But basically, it's a representative sample, we think, of all the folks who are actually raising money.
And again, this is the raising money side. It's like, I need to go out to either the equity markets or the capital markets and actually raise capital. And that then funds capital expenditure. So in a way, it's almost the leading indicator, right? You raise finance today to spend it tomorrow.
But it's also this, you could look at it as a new trend among certain developers. Like they may have been just developing data centers using their own money, which to this exercise is sort of invisible. And the raising of money specifically for building data centers is kind of an indication that that well has run dry. And so they're now having to go out and look for like additional capex to continue this need to build more and more data centers everywhere.
“Meta, Amazon, Google are free cash flow negative, which means that they're actually spending more than they are generating.”
It's interesting. I mean, I know you've laid out all of these different types of organizations. It's not just about the hyperscalers. No. But it's interesting. As you say, these most profitable and big companies in the history of capitalism have never needed to get money from anywhere because they're getting it from their business. And we're at a point where they're spending so much, they're needing to raise money. Yeah. So talk us through how this works, like the lifecycle
“And all the liability is actually what's called ring fenced to a given project. And so it's a really proven strategy for infrastructure development”
So actually on the former, there's a huge difference. Again, I.
“The natural correlate of that is if you're raising a ton of money today, it's going to be due pretty soon.”
So that's a big part of the game here. Because it's such an intense moment of huge investment is the efficiency at which you can refinance and make sure that you rebalanced the time scales on which debt is going to be due so that it extends beyond this construction boom.
Well, it's more like there's so much maturing in a small amount of time that people need to want to be aware of that and just go clear-eyed into that. The other thing I'd mention is that some of the debt that has been raised was raised a few years ago. And anyone who's followed the US treasuries or just broader market has known that interest rates have gone up. If you're trying to buy a house, you know that interest rates have gone up tremendously in the last three, four years. So some of it is almost mechanical where if you're refinancing debt that you issued a few years ago, and it's suddenly two, 3% higher, just because the US Treasury is two or 3% higher, then that's obviously going to impact your costs of capital tremendously. So there's some of that is just like market has moved to a tougher financing environment. Some of that is dependent on your ability to really execute on your pipeline. So like, can you build this data center on time and on budget? If yes, then you're owning, again, this incredibly valuable commodity.
And your team has done great work on this. Others in BNF have done great work on pointing out that there's a lot of challenges in actually executing on building a data center.
Yeah, it takes time. And it's really interesting the point you make about how treasuries go up and you haven't refinanced yet. You're holding a little, it's like a hot potato type situation. You really need to offload that as quickly as you can. You need to complete construction as quickly as you can. I want to go back to talking about loan guarantees because I'm sure there's a lot of listeners who want to maybe drill into like what we were talking about when you said actually the company that's done the most in terms of loan guarantees is NVIDIA. At the time we're recording this podcast, the CEO of NVIDIA has been embroiled in a scandal. You know, by the time you hear this, I don't know where we're going to be in that whole story. But given that that company, I'm assuming that that doesn't really affect NVIDIA.
loan guarantees they've already made, but it might be with change happening at that company and also their share price being lower, their either willingness or ability to carry on with that model may change. Do you think that could have a significant impact on the ability for a lot of companies to get data centers financed and therefore the general momentum that sits behind this industry?
And so first, just to talk about the share price, it obviously matters because it a signal about how the market views the health of a given company. But for this, it's actually irrelevant in the short term. And I just want to touch on that aspect. NVIDIA, what you really want to look at is what is their cash balance? So how much money do they have on their balance sheet? Because whatever their price is doing in the stock market doesn't really impact.
Those are transactions between third parties. Right. So just to say that as like some people might be like, oh, my God, their stock's down. It's like, well, that doesn't really matter for this.
But does it it does influence where the limit on how much in total lenders are willing to. It's kind of a proxy, right?
It's just like it's a signal the same way some of these other metrics we can talk about as well. are about how the market is viewing the health of, in this case, NVIDIA, or even just the broader AI financing ecosystem. But to get really specific about the point, because they are crucial, I would say.
“NVIDIA is basically providing a revenue floor. They're saying, you're going to make at least this much money with us”
And have you seen the hyperscalers go up? Because you mentioned, you know, you could interpret what NVIDIA has been doing is trying to cultivate an ecosystem of, say, non-giants doing AI, using open source code, like to, in a way, take away some of the power that's concentrated in the big tech companies. So have their share prices?
I believe they have, although it's also more complex because they're not just chip makers. It's how much is their, you know, in the hyperscale, how well is their cloud revenue performing? Yeah, there's so much going on. Is their cash balance good? Yeah, there's all these questions like, are their models performing in the case of like Google or Meta? Yeah, a lot in there.
We talked a little bit about the way that, say, companies like NVIDIA, and you mentioned AMD, might be using these loan guarantees to jockey for position, if you could, or to try and shape the industry in their image. Do you feel like these other players you mentioned, the hyperscalers, the neoclouds, the co-location companies, do they all have their own version of this where, to some extent, this is not just about scaling, it's about having slightly sharp elbows on the edges?
I don't think they would say that. I think they would say, you know, it's not a zero sum game. But at the end of the day, I mean, part of the way to think about this whole ecosystem is from the lens of demand. So, I mean, what is the thing that all of these data center developers are selling? So in the case of the neoclouds and the hyperscalers, that is access to computing capacity, whether it's the chips themselves or it's the tokens that are produced by the chip. And the token obviously is kind of the unit of AI as we talk about it. Some folks would dress it up and say, oh, token is intelligence, if you want to frame it that way. The co-location providers providing access to the data center, which are then used by the others to produce, you know, intelligence produced tokens. And so the demand for those right now is coming a lot from the Frontier Labs. So we haven't really talked about it that much, but OpenAI and Anthropic are a lot of the end customers for this. So it really depends on where you sit in the chain. So are you competing for an Anthropic contract like the Neoclouds are?
So they're certainly competing against each other. Certainly the hyperscalers are competing, again, to serve OpenAI and Anthropic. but also a host of other companies. I mean, again, they have huge cloud businesses with the exception of Meta. And so they're competing to serve their existing clients, add new clients, really pivot to embedding AI services. And then the co-location providers are, they're really, I would say, if we're going to get into it, competing for a few investment grade clients. Because actually, from their perspective, it is, again, because it enables them to raise finance, they need an investment grade client or they need an investment grade guarantor or they need someone in there whose credit is rock solid or else a bank is not going to finance them and then they might have to go and we haven't talked about it at all but might have to rely on on private markets players as well who are more flexible in their arrangements.
“they only have, I think, less than 50% of their financing coming from private sources”
So we started talking about huge numbers in terms of money. I want to just talk about where this ends. Because I think it's no surprise that this is one of the biggest technological trends we've seen in the history of mankind. It's also, we're talking about some of the biggest companies in the world. Yeah. So there's been, you know, an absolutely astronomical amount of money being raised and being invested. I think it's fair to say, you know, you just look at the ratios that this isn't going to continue forever. At some point in this level of financing, maybe I'm wrong. Acceleration, yeah. Something's going to slow down.
Mm-hmm. And then you mentioned a lot of debt that we're talking about here is maturing in the early 2030s, the way we're looking at. So what does the future look like? Does it look like here in the mid 2020s, a huge amount of investment happens as a lot of companies rush to stake their position in this AI future? and then it's sort of like they all hold their breath five to six years during the construction phase of a lot of what's happening and if things are going to go wrong with this investment that might be when it might all go wrong so the early 2030s are when this hopefully for the companies involved all emerges healthily this was a good idea to commit so much capital is that the kind of the timeline we're looking at in terms of the success or failure of what's happening right now.
“I think the next 12 months are really going to be a big litmus test for is there enough value return on investment in the short term.”
Yeah yeah because also there's a lot of other people asking for there's a lot of exactly that's part of it i mean you we could get into a whole discussion about how it's all this demand is actually pushing up maybe the u.s treasury as well the base rate. Such a fascinating, a fascinating topic in, you know, I don't think there's been any kind of, I'm not an expert on these things, but the amount that's being invested in this particular infrastructure is in such a short space of time, it's sort of unprecedented. And we are looking at therefore an unprecedented event happening over the previous few years, over the next few years in the financial markets. And there's so many different dynamics. So, so many unanswered questions.
We need like a whole podcast series about this. But thank you, Elise, for introducing me and our listeners to these questions because they are going to be consequential for the future of the AI industry, for the future of energy. Oh, certainly. For so many other, you know, I don't even want to go there. Yeah, the global economy for geopolitics. So much is riding on how this plays out. And there's quite a lot going on. So, been really good talking to you today. Thank you. Today's episode of Switched On was produced by Cam Gray with production assistance from Kamala Schelling. BloombergNEF is a service provided by Bloomberg Finance LP and its affiliates. This recording does not constitute nor should it be construed as investment advice, investment recommendations, or a recommendation as to an investment or other strategy. BloombergNEF should not be considered as information sufficient upon which to base an investment decision.
Neither Bloomberg Finance LP nor any of its affiliates makes any representation or warranty as to the accuracy or completeness of the information contained in this recording and any liability as a result of this recording is expressly disclaimed.